How to write a construction safety program

A written safety program is your company's safety rules on paper. It says who is in charge, how you find and fix hazards, how you train crews and what you do after an injury. OSHA has no single rule requiring one, but many standards require written plans. Some states require a full program, and GCs ask for it.

This guide covers the federal OSHA construction standards, the states that require a full program, what GCs check in prequalification, and how to write a program your crews will use. It is not legal advice. Check the current rules before you rely on them. Companies named here, like Uinta Roofing Co., are fictional.

What a written safety program is

A written safety program says how your company keeps workers from getting hurt. It covers your policy, who is responsible for what, the hazards on your jobs, the controls for each one, training, inspections, and what happens after an injury.

It goes by other names. A safety manual, an accident prevention program and an injury and illness prevention program (IIPP) are usually the same document. If you searched for a safety manual template or a construction safety manual template, this is it. The company program covers all your work. A site-specific safety plan covers one project.

Who reads it

What OSHA actually requires in writing

People search for an "OSHA written safety program" as if it were one form. It isn't. Federal OSHA has no construction standard titled "safety program." The closest is 1926.20(b). It makes employers responsible for the programs needed to comply with the construction standards, including frequent and regular inspections by competent persons. 1926.21(b)(2) requires you to instruct each employee in recognizing and avoiding unsafe conditions.

Neither says the program must be written. Specific standards do. If your crews face certain hazards, the standard for that hazard requires a written program or plan. These are the ones a sub is most likely to need.

Written programStandardWhen it's requiredWhat it must contain
Hazard communication program1910.1200(e), via 1926.59Your crews work with hazardous chemicals. Products with a Safety Data Sheet (SDS), like sealants, fuels, solvents and cement, are the usual sign.A list of your hazardous chemicals, named as on the SDSs. How you meet the label, SDS and training rules. How you warn workers about non-routine tasks. On shared sites, how other employers get your SDSs and labeling information.
Silica exposure control plan1926.1153(g)Work that exposes workers to respirable crystalline silica, like cutting, drilling or grinding concrete, masonry, stone or tile. Exempt only if exposure stays below 25 µg/m³ as an 8-hour average under any foreseeable conditions.The tasks that expose workers. The controls, work practices and respirators for each task. Housekeeping. How you restrict access to the work area. A competent person who inspects. A review at least once a year.
Respiratory protection program1910.134(c), via 1926.103Respirators are needed to protect workers, or you require them. Voluntary dust masks alone need no program, just a copy of Appendix D of 1910.134 for each user.Worksite-specific procedures for selection, medical evaluation, fit testing, use, maintenance, training and checking the program works. A trained program administrator. No cost to workers.
Fall protection plan1926.502(k)Leading-edge work, precast concrete erection or residential construction, when you can show conventional fall protection is infeasible or creates a greater hazard.Prepared by a qualified person for one site and kept there. Supervised by a competent person. Why conventional protection can't be used, what you'll do instead, controlled access zones and who may enter them, a safety monitor where nothing else is used, and an investigation after any fall or near miss.
Emergency action plan1926.35Only when another OSHA standard requires one. OSHA recommends one for every employer. With 10 or fewer employees it may be oral.Escape procedures and routes, critical operations, a head count, rescue and medical duties, how to report emergencies, and who to contact. An alarm system and training.
Permit-required confined space program1926.1203(d), Subpart AAYour workers will enter a permit-required confined space.A program meeting 1926.1204, in place at the site and available to workers. An entry permit before each entry (1926.1205).
Lead compliance program1926.62(e)(2)Before any job where exposure may reach the limit of 50 µg/m³ as an 8-hour average, such as work that disturbs lead paint.Each lead task and its controls, how you'll comply, monitoring data, a schedule, work practices and how contractors on a shared site split the work. Kept at the worksite and updated at least once a year.
Assured equipment grounding conductor program1926.404(b)(1)(iii)Only if you use it instead of GFCIs on temporary 120-volt, 15 and 20 amp receptacles.A written description of your procedures at the jobsite, run by a competent person.

Each of these plans has to describe your actual work. A hazard communication program template is useless until it lists your products. A silica exposure control plan template has to name your tasks and controls. A fall protection plan template only becomes a plan when a qualified person completes it for one site.

Other records the standards require in writing

RecordStandardWhat it is
Fall protection training certification1926.503(b)Each trained worker's name, the training date, and the trainer's or employer's signature.
Excavation protective system data1926.652(b) and (c)Tabulated data or an engineer's design, in writing, with a copy at the jobsite.
Formwork and shoring drawings1926.703(a)(2)Plans for the jack layout, formwork, shoring, working decks and scaffolds, at the jobsite.
Steel site-specific erection plan1926.752(e)Needed when you use certain alternate methods allowed in Subpart R. Developed by a qualified person and kept at the site.
Demolition engineering survey1926.850(a)A competent person's survey of the structure before demolition, with written evidence it was done.

Lockout and tagout in construction

OSHA's general industry lockout standard, 1910.147, requires written energy control procedures, but it excludes construction. In construction, 1926.417 requires tags on deenergized circuits and their controls. 1926.702(j) requires mixers, pumps and similar concrete and masonry equipment to be locked and tagged out before servicing. Neither requires a written program. Writing your lockout steps down is still the clearest way to train them.

Emergency action and fire prevention plans

1926.35 sets the contents of an emergency action plan when another standard requires one. OSHA's construction Quick Start recommends one for every employer. For fire, 1926.24 and 1926.150(a)(1) require a fire protection and prevention program on every job site, but don't say it must be written. The written fire prevention plan in 1910.39 applies only when a general industry standard calls for it.

Put your extinguisher rules in the program anyway. 1926.150(c)(1) calls for a 2A extinguisher for each 3,000 square feet, within 100 feet of travel. It calls for a 10B extinguisher within 50 feet of where more than 5 gallons of flammable or combustible liquid is used. The free builder puts an emergency action plan with these rules in every program.

Competent and qualified persons

Many standards don't require a written plan but do require a named person. A competent person can identify existing and predictable hazards and has the authority to correct them promptly (1926.32(f)). A qualified person has a recognized degree, certificate or professional standing, or extensive knowledge, training and experience (1926.32(m)). The responsibilities section below lists their duties.

OSHA's Recommended Practices, the voluntary framework

In October 2016 OSHA published Recommended Practices for Safety and Health Programs in Construction (OSHA 3886). It is guidance, not a rule. OSHA says it won't cite an employer because its program doesn't follow it. The seven core elements are:

  1. Management leadership
  2. Worker participation
  3. Hazard identification and assessment
  4. Hazard prevention and control
  5. Education and training
  6. Program evaluation and improvement
  7. Communication and coordination for employers on multiemployer worksites

OSHA says small employers may meet them with informal communication and procedures. It also says finding and fixing hazards should be done site by site. The free builder takes the same hazard-by-hazard approach. Say you use products with an SDS and it writes a hazard communication program. Say you cut concrete or tile and it writes a silica plan with the Table 1 tasks your trade usually does.

States that require a full program

Some states run their own OSHA program, called a state plan. A few states go further than federal OSHA and require one written program for your whole operation. We checked these against state sources. If you work in California, an injury and illness prevention program template is the usual starting point. It only counts once it has your names, your inspection schedule and your training records.

StateRuleWho must have oneWhat it requires
CaliforniaIIPP, 8 CCR 3203. Construction adds 8 CCR 1509.Every employer.A written program naming who runs it, with systems for compliance (such as recognition, training or discipline), communication, scheduled inspections, injury investigation, hazard correction and training. Inspection and training records kept at least one year. Construction adds a written Code of Safe Practices and toolbox meetings at least every 10 working days. Employers with fewer than 10 employees may communicate orally and keep lighter records.
WashingtonAccident prevention program, WAC 296-155-110Construction employers.A formal program tailored to your work and outlined in writing. A safety orientation for new workers. Crew safety meetings at the start of each job and at least weekly, with minutes kept one year. Weekly walk-around inspections.
MinnesotaAWAIR, Minn. Stat. 182.653, subd. 8Industries listed in Minn. R. 5208.1500. The list now includes every code in NAICS 237 (heavy and civil) and 238 (specialty trades), but not building contractors in 236.A written program with goals, responsibilities, hazard control, communication, accident investigation and rule enforcement. Reviewed and documented every year.
NevadaNRS 618.383, NAC 618.540Employers with more than 10 employees.A written program covering responsibilities, hazard control, training before work, accident investigation and rule compliance, in a language and format each worker understands. A safety committee above 25 employees.
OregonOAR 437-001-0765Most employers.No general written program rule. A safety committee, or safety meetings if more than half your employees report to construction sites. Construction meetings at least monthly and before any job over a week, with written records kept three years.
UtahUOSH, Utah Admin. Code R614-1Employers under Utah's state plan.No general written program rule that we found. The federal written programs apply. R614-1-5 adds the duties below.

Utah under UOSH

Utah runs its own plan through Utah Occupational Safety and Health (UOSH), part of the Utah Labor Commission. R614-1-4 adopts federal Part 1926 by reference, using the July 1, 2024 edition, so the federal written programs above apply in Utah. R614-1-5 adds duties that belong in any Utah program:

The builder is written for work in Utah for now. Its Utah section covers UOSH's adoption of the federal standards and the 8-hour reporting rule. In another state, use it as a base and add that state's rules from the table.

Heat illness plans

There is no final federal heat standard yet. OSHA proposed one in August 2024 and has not issued a final rule. California's 8 CCR 3395 covers construction and requires a written heat illness prevention plan in English and the language most of your employees understand. Washington requires outdoor heat exposure to be addressed in the written accident prevention program (WAC 296-62-09530).

What GCs look for in prequalification

Prequal forms ask about safety in three ways. They ask whether you have a written program. They ask about results, like your EMR, OSHA 300A data and citations. And they ask how the program runs day to day, meaning meetings, inspections and who is in charge.

What public prequal forms ask

Public agencies publish their forms, so they show what reviewers look for. Three examples:

Private GCs write their own forms. Expect the same three kinds of questions, plus requests for OSHA 300A summaries, training records and toolbox talk sign-in sheets. Our guide on how to prequalify subcontractors shows the full checklist from the GC's side.

What makes a program pass or fail

A reviewer reading your program is asking one question. Does this company actually run it?

What they checkPassesFails
Trade-specificSections match the work you bid. A roofer's program covers roof edges, ladders, hot work and heat.A generic manual with forklift chapters and nothing about roofs.
SignedThe owner signed and dated the policy. Workers signed an acknowledgment.No signatures, or signed by someone who left.
CurrentA review dated in the last year, with the right company name and administrator.An old company name or a review years ago.
Named peopleA program administrator and a competent person for each hazard."A competent person will be designated."
Backed by recordsTraining records, toolbox talk sign-ins and inspection checklists that match the program.Weekly inspections promised, no inspection records.
Consistent with resultsSteady or improving EMR and TRIR, or changes made after an incident.Rising injury rates and a program that never changed.

The builder gives you the pieces reviewers look for. Each program has a signature line on the policy, a review log, an employee acknowledgment sheet, a training record, a chemical list and a dated toolbox talk calendar. You still have to sign them, fill them in and use them.

What goes in a good program

Whatever your state, a good program has the same core sections. They line up with OSHA's seven recommended elements and California's IIPP elements. Keep each one short and specific to your company.

Management commitment and policy

One page, in plain words, signed and dated by the owner. Say no schedule or cost is a reason to work unsafely. Say every worker can stop unsafe work without retaliation. Name the program administrator and give that person authority to stop work and buy safety equipment.

Responsibilities, including competent and qualified persons

Say what the owner, the administrator, foremen and workers each do. Say that on a GC's site, crews follow the GC's site plan too, and the stricter rule wins. Then name your competent and qualified persons. These are the duties the standards give them.

DutyWhoStandard
Frequent and regular inspections of job sites, materials and equipmentCompetent person1926.20(b)(2)
Inspect scaffolds before each shift and supervise erecting and dismantlingCompetent person1926.451(f)(3), (f)(7)
Train workers exposed to falls, and ladder usersCompetent person1926.503(a)(2), 1926.1060(a)
Inspect excavations daily and after rainCompetent person1926.651(k)(1)
Inspect under the silica planCompetent person1926.1153(g)(4)
Identify confined spaces before work startsCompetent person1926.1203(a)
Supervise work under a fall protection planCompetent person1926.502(k)(4)
Survey a structure before demolitionCompetent person1926.850(a)
Prepare a fall protection plan and approve changesQualified person1926.502(k)(1), (k)(2)
Train scaffold usersPerson qualified in the subject1926.454(a)

Hazard identification and job hazard analysis

Say how you find hazards. The foreman checks the area before work. Competent persons do their required inspections. Workers report hazards. And you write a job hazard analysis (JHA) for your riskiest tasks. OSHA's JHA booklet (OSHA 3071) describes it as finding hazards before they happen by looking at the task, the worker, the tools and the work environment together. Here is a short one for Uinta Roofing Co.'s tear-off on a steep residential roof.

StepHazardControl
Set up the ladderLadder slips at the eaveRails extend at least 3 feet above the landing (1926.1053(b)(1)). Tie the ladder off at the top.
Install anchorsFall before anyone is tied offAnchors hold 5,000 pounds per worker, or are part of a complete system with a safety factor of two, supervised by a qualified person (1926.502(d)(15)).
Tear off shinglesFall from the roofEach worker wears a harness tied off to an anchor.
Throw debris to the dumpsterDebris hits people belowBarricade the drop area. Nobody walks under the work.
Summer workHeat illnessWater, shade and rest breaks. Start early on hot days.

Training and documentation

Train at hire, before a new task, tool or chemical, after an incident, and at regular toolbox talks. Some standards set their own rules. Hazard communication training comes at first assignment and with each new chemical hazard (1910.1200(h)(1)). Fall protection training comes from a competent person, with a written certification (1926.503). Only trained workers run powder-actuated tools (1926.302(e)(1)). Respirator users are fit tested before first use and every year (1910.134(f)(2)). Record each session with the date, topic, trainer and each worker's signature. Utah and Nevada both require training in a language workers understand.

Inspections

Write down who inspects, how often and on what form. The foreman checks the area each day. Competent persons do their required inspections. The administrator walks each site on a set schedule and records what was found and fixed. Unsafe equipment is tagged, locked out or removed from service, as 1926.20(b)(3) requires. Washington requires weekly walk-around inspections. California requires scheduled inspections and records of them.

Incident reporting and investigation

Workers report every injury, illness and near miss to the foreman the same shift. You investigate to find the cause and fix it, not to blame. Write down your deadlines:

Discipline

A rule nobody enforces is a suggestion. California's IIPP needs a system for making workers follow safe practices, which can include discipline. Minnesota's AWAIR program and Nevada's program must say how you enforce safety rules. Write a short progressive policy. A first offense gets a verbal warning and retraining, a second a written warning, a third suspension or termination. Serious violations, like working at height untied, can mean removal from the job right away. Apply it to foremen too. The free builder includes a stepped discipline section you can adjust to match how your company handles it.

Emergency procedures

Cover the emergency action plan elements in 1926.35(b), from reporting and the alarm to exits, head count and rescue duties. Arrange prompt medical attention before the project starts (1926.50(a)). If no clinic, hospital or doctor is reasonably accessible, have a worker with valid first aid training on site (1926.50(c)). Plan how you'll rescue anyone caught in a fall arrest system, since 1926.502(d)(20) requires prompt rescue.

Recordkeeping

If you had more than 10 employees at any time last calendar year, keep the OSHA 300 log, 301 reports and 300A summary (1904.1) for five years after the year they cover (1904.33). Our OSHA 300A guide explains how. Keep training records, inspection records, toolbox talk sign-ins and investigations with the program too.

Working with GCs and sub-tiers

On a multi-employer site, OSHA's citation policy (CPL 02-00-124) can reach the employer that created a hazard, the one whose workers are exposed, the one responsible for fixing it and the controlling employer. Your program should cover both directions.

Trade-specific sections

The rest of the program is one section for each hazard your crews face. Each says what the rule is, what controls and PPE you use, and who trains and inspects. Cite the standard so a reviewer can check it.

Need a written safety program for your next prequal?

Answer about a dozen questions and get a program written for your trade, citing the OSHA standard each section covers. Free.

How to write one, step by step

This is the order we'd follow for a small sub writing a first program or replacing a generic one.

  1. List your work and your hazards. Write down your trade, your typical tasks and what crews are exposed to. Think about heights, ladders, scaffolds, dust, chemicals, tools, trenches, cranes, equipment, live electrical parts, hot work, noise, heat, confined spaces and old paint. The free OSHA safety program template builder starts here. It pre-checks the hazards your trade usually has, and you change what doesn't fit.
  2. Find the written programs those hazards trigger. Use the OSHA table above. Concrete dust means a silica plan. Products with an SDS mean a hazard communication program.
  3. Check your state. In California, Washington, Minnesota or Nevada, cover every element your state lists. In Utah, add the 8-hour reporting rule and the emergency contact list.
  4. Write the policy and have the owner sign it. Name the program administrator.
  5. Name your people. Pick the competent person for each hazard and any qualified persons you need.
  6. Write a section for each hazard. Give the rule, controls, PPE, training and inspections, and cite the standard. Add JHAs for your riskiest tasks.
  7. Add the procedures that run the program. Training, inspections, incident reporting, discipline, emergencies, recordkeeping, and GCs and sub-tiers.
  8. Build the forms. An acknowledgment, a training record, an inspection checklist, an incident report, a chemical list and a toolbox talk calendar.
  9. Train every worker on it. Walk each crew through the parts that apply to them and collect signed acknowledgments.
  10. Have it reviewed and set the next review date. Have a qualified safety professional review it. OSHA's On-Site Consultation Program gives small businesses free, confidential advice, separate from enforcement. In Utah, UOSH runs it without citations or penalties.

Here is how that went for Uinta Roofing Co., a fictional Utah roofer with 14 employees. The owner picked roofing. The builder pre-checked work at height, ladders, products with an SDS, power tools, torches and hot weather. The owner added cutting concrete tile and a crane service for loading. The program came back with sections for fall protection, ladders, hazard communication, silica, power tools, cranes, hot work and heat, plus the sections every program gets. The owner added a discipline policy and a tear-off JHA, signed the policy, and trained the crews at the next Monday toolbox talk.

Trade-specific sections

This table lists what each trade usually needs. Your work may add more. A plumber who digs their own trenches needs the excavation section too.

TradePrograms and topics it usually needs
RoofingFall protection for low-slope roofs (1926.501(b)(10)) and steep roofs (1926.501(b)(11)). A fall protection plan only where 1926.502(k) allows one, such as residential work where conventional protection is infeasible. Ladders. Hazard communication for adhesives and primers. Hot work for torch-applied systems (1926.352). Silica if you cut concrete or clay tile. Heat.
Framing and carpentryFall protection, including residential work under 1926.501(b)(13). Ladders and scaffolds. Power tools, GFCIs and powder-actuated tool training (1926.302(e)). Noise. Heat.
Concrete and masonrySilica plan with Table 1 tasks (1926.1153). Hazard communication for cement. Formwork drawings at the jobsite (1926.703(a)(2)). Lockout and tagout of mixers and pumps (1926.702(j)). A limited access zone for masonry walls (1926.706(a)). Scaffolds. Noise. Heat.
ElectricalElectrical safety and tagging of deenergized circuits (1926.416, 1926.417). GFCIs or an assured equipment grounding conductor program (1926.404(b)(1)). Nonconductive ladder side rails near energized equipment (1926.1053(b)(12)). Silica for drilling and coring. Aerial lifts. Arc flash procedures for energized work. NFPA 70E is the consensus standard for them.
Plumbing and HVACTrenching (Subpart P). Confined spaces (Subpart AA). Hot work for brazing and soldering (1926.352). Silica for core drilling and chipping. Hazard communication for solvents, cements and refrigerants. Ladders and lifts. Electrical safety for HVAC.
Drywall and paintingLadders, scaffolds and aerial lifts. Hazard communication for compounds, paints and solvents. Respiratory protection where respirators are required. A lead compliance program before work that disturbs lead paint (1926.62).
Excavation and siteworkTrenching, with daily competent person inspections (1926.651(k)), protective systems at 5 feet (1926.652) and written data at the jobsite. Locating utilities before digging (1926.651(b)). Heavy equipment (Subpart O). Silica for saw cutting and breaking. Noise. Heat.
Steel erectionSubpart R fall protection, including protection above 15 feet and connector and decking zone rules (1926.760). The controlling contractor's written approval to begin (1926.752(a)). A site-specific erection plan for alternate methods (1926.752(e)). Crane operator certification (1926.1427). Hot work.
DemolitionA written engineering survey before work (1926.850(a)). Silica. Lead. Respiratory protection. Heavy equipment. Hazard communication. Noise.

The builder covers 20 trades, from roofing and concrete to fire sprinklers and landscaping, plus a "something else" option. Picking a trade pre-checks its usual hazards and silica tasks. You can change any of them, and the sections follow your answers.

Site-specific safety plans

A site-specific safety plan (SSSP) applies your company program to one project. Your program says how you handle fall hazards on any job. The SSSP says where the fall hazards are on this job, which anchors you'll use and who the competent person is on site. The program is reviewed once a year. The SSSP is written before you mobilize and changes as the job changes.

The requirement for an SSSP usually comes from the GC or owner, not OSHA, so check your subcontract and the project's safety requirements. Some OSHA plans are site-specific by rule, like a fall protection plan under 1926.502(k) or a steel erection plan under 1926.752(e). Those go inside the SSSP.

Site-specific safety plan template

Use this outline as a construction safety plan template for each job. Keep it short enough that your foreman will read it.

SectionWhat to include
1. Project informationName and address, owner, GC, your scope, dates, crew size and work hours.
2. ContactsYour project manager, foreman, administrator and competent persons, with phone numbers. The GC's superintendent and safety contact.
3. Scope and hazardsEach phase of your work and its hazards, such as roof edges, openings, power lines, trenches, silica dust, crane lifts and nearby trades. A JHA for each high-risk task.
4. ControlsThe control for each hazard and who is responsible. Guardrails or tie-off points, Table 1 silica controls, trench protection, PPE, barricades.
5. Emergency informationThe site address for responders. The nearest hospital or clinic with address, phone and route. The assembly point and head count. First aid trained workers. The fall rescue method. In Utah, the emergency list R614-1-5 requires.
6. Permits and plansConfined space entry permits, hot work permits if the GC requires them, utility locate tickets, crane lift plans, and any fall protection or steel erection plan for this site.
7. TrainingThe GC's orientation, your project briefing, and the certifications each worker needs on this job.
8. Sub-tier coordinationYour sub-tiers, their scopes and competent persons, and how you share SDSs, schedules and hazards with them and the GC.
9. Sign-offSigned by your project manager and foreman, with a line for the GC and a log for changes.

The builder writes your company program, not a site plan. Most of the SSSP comes from it, though. Use its hazard sections for parts 3 and 4, its emergency action plan for part 5 and its training section for part 7. If you need a fall protection plan, it gives you a page to copy and complete for each site.

Keeping it alive

A program that sits in a binder fails the first time someone compares it to the job site. These habits keep it current.

Review it at least once a year

Some plans set their own review rules. The silica plan is reviewed at least once a year (1926.1153(g)(2)). The lead program is updated at least once a year (1926.62(e)(2)). Minnesota's AWAIR program needs a documented yearly review. The respirator program needs regular checks that it works (1910.134(c)(1)(ix)). Update the chemical list when a new product arrives. The builder's program ends with a review log and calls for a review at least once a year.

Update it after incidents and changes

After a serious injury or near miss, ask whether the program covered the task. If not, fix it and retrain. Do the same for new kinds of work, equipment, chemicals or states. Washington's weekly crew meetings must review accident investigations to check the causes were found and fixed.

Hold weekly toolbox talks

Toolbox talks carry the program to the crew. Washington requires crew meetings at least weekly, California at least every 10 working days, and Oregon at least monthly for construction. Weekly is a safe default, with a sign-in sheet for each talk. Our 52 construction toolbox talks give you a year of topics and a printable sign-in sheet. The builder adds a calendar of talks, weekly or every two weeks, matched to your hazards, with heat and cold topics in season.

Watch your EMR and TRIR

Your results show whether the program works. Your experience modification rate (EMR) compares your workers' comp claims to what is expected for your trade and size. It is built from several past years of claims, so it moves slowly. Our EMR guide explains it. Your total recordable incident rate (TRIR) is recordable cases times 200,000, divided by hours worked. The 200,000 stands for 100 full-time workers for a year. Work yours out with our TRIR and DART calculator. GCs compare both year over year. Fewer and less severe injuries bring both down over time.

Common mistakes

Using a generic downloaded manual

A long manual from the internet covers forklifts and machine guarding but not your roofs or trenches. Reviewers notice. It may also promise programs you don't run, which an inspector can hold you to.

Leaving it unsigned

An unsigned policy says management never read it. The owner signs the policy, each worker signs an acknowledgment, and the administrator signs each review.

Skipping the trade sections

A policy and an org chart with nothing about your hazards isn't a safety program. The hazard sections are where the rules live.

Never training on it

If crews have never seen it, it doesn't protect them, and it won't hold up in prequal. Train new hires on it, cover pieces at toolbox talks and keep the signed records.

Letting it go out of date

An old company name, an administrator who left, or no silica plan when you now cut concrete all say the program isn't used. Review it yearly and after big changes.

Writing rules you don't follow

If the program says daily inspections, you need daily inspection records. Write what you will do, then do it.

Frequently asked questions

Does OSHA require a written safety program for construction?

Not as one document. Federal rule 1926.20(b) requires construction employers to run safety programs with frequent and regular inspections by competent persons, but it does not say the program must be written. Specific standards do require written programs, such as hazard communication, silica exposure control and respiratory protection. California, Washington, Minnesota and Nevada require a full written program for the employers they cover.

Do I need a written safety program if I have 10 or fewer employees?

Usually yes. The hazard communication and silica plans depend on the work you do, not your size. A few rules ease up for small employers. With 10 or fewer employees you may give an emergency action plan orally, and you may not need OSHA injury logs. GCs ask for a written program regardless of size.

What is the difference between a safety program and a site-specific safety plan?

Your safety program is your company's rules for all your work, reviewed every year. A site-specific safety plan applies those rules to one project. It lists that site's hazards, controls, contacts, nearest hospital, permits and sub-tiers. The GC or owner usually requires it in the subcontract.

Can I use a free safety program template?

Yes, as a starting point. A template only works once you fit it to your trade, your state and your crew, sign it and train on it. The free builder on PreQualifySubs.com writes sections from your answers about your work, so you start closer to finished. Have a qualified safety professional review any template before you rely on it.

How often should I update my safety program?

Review it at least once a year. The silica plan and the lead compliance program each need a review at least yearly. Also update it after a serious incident, when you take on new work, tools or chemicals, and when the people named in it change.

Who should sign the safety program?

The owner or a company officer signs and dates the policy statement. Each worker signs an acknowledgment that they received the program and were trained on it. The program administrator signs each annual review.

What do GCs want to see besides the program?

The public prequal forms we reviewed asked for your EMR for the last three years, recent OSHA citations, how often you hold documented safety meetings and inspections, and who runs safety. GCs also ask for OSHA 300A summaries, training records and toolbox talk sign-in sheets.

Is the PreQualifySubs.com safety program builder free, and does it work outside Utah?

It is free. You answer about a dozen questions and preview the start of your program in your browser. To get the full program, you save it to a free PreQualifySubs.com account and we email you a PDF copy. For now it is written for work in Utah under UOSH. In another state, use it as a starting point and add that state's rules.

Sources

Checked November 15, 2026. Rules change, so confirm against the source before you rely on them.